A: I was directed to finish this in the week of June 13th or the world will end. I wish I can be Magneto for a week. Need to find options. Need to propose a solution even if you don't think this is feasible.
B: Once frames are delivered there is then a lead time to get all the baffles installed. The only thing I could suggest is trying to expedite galv and/or working our guys 7 days a week once delivered.
A: Please let me know the possibilities as discussed this morning. Thanks!
B: I have compiled the costs associated with this, I am just waiting to hear back from galv on what can be done to expedite things on their end.
A: Thanks! The earlier the info is available the earlier we can make a decision on this.
B: So here is what we have managed. Total costs in galv premiums and our fab OT premium would be $3x,xxx.00.
A: Thanks for the effort! I've forwarded the cost to the upper management for their decision.
A: 90% go. Still waiting for the final decision.
A: The final answer is ... no go.